Hi @GIna Romero
When you say Team Capacity, do you mean the team's velocity?
If yes, on your board's side-menu, there is a Reports option - in here, you can find the Velocity Report. This will begin to populate as you start closing sprints.
The report will use issue count by default - or use story points if you have activated Estimation for the project and populated the estimates prior to the sprint.
To activate Estimation:
If this is not what you were looking for, let us know what Team Capacity means to you so we can assist you further :)
Ste
Thanks for the quick response! However, I do mean team capacity...example during sprint planning I need to know the time capacity in hours of the dev each team member, the holiday time off I have to factor for the team, etc. so that I can calculate the total team capacity for a sprint.
Any help is appreciated.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @GIna Romero
Natively, this isn't available for Next-Gen or Classic Projects.
You would need to consider an app for this - such as Team Capacity Planning - or upgrading to Jira Cloud Premium - which has Advanced Roadmaps built in - with Teams are available. See more about how these work on this page.
I would trial these though with Next-Gen - some of their functionality might differ between Next-Gen and Classic Boards.
Ste
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.