Jira Next-Gen documentation indicates that issues on the done column past 14 days would automatially be archived and removed from the board (with sprints turned off). This is not the case. Am I doing something wrong or is this a bug?

2 answers

1 accepted

0 votes
Answer accepted
Adam Shia January 31, 2019

I've received an answer from Atlassian support on this matter:

 "I've taken a look at the board and I noticed that the issue has been moved to Done since the 15th of January. The issue is not removed from the board because there is an update on the issue, which is 7 days ago. This refreshes the 14 days timer, hence why the issue is still appearing in the board.

We have a feature request to change this, instead of any updates on the issue, Jira should only count the 14 days since the issue is resolved:

I would suggest you to vote for this issue to raise the popularity."

Tim Kersten February 13, 2019

I'm having similar issues, but the last updated time on the tickets are over 30 days ago in my case...

I opened a question at https://community.atlassian.com/t5/Questions/Issues-not-disappearing-from-next-gen-software-board-when-Done/qaq-p/1006558

This looks like a bug, and not the behaviour outlined in your discription.

Like John Minne likes this
0 votes
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 31, 2019

Hello,

Issues in the most right column are removed after 14 days. Is your Done column the most right column?

Adam Shia January 31, 2019

Yes. See screenshot. What is the date criteria for the 14 days to kick in?

 

 Untitled.png

Thomas Serio March 23, 2019

We noticed a ton of our tasks in the rightmost column were not rolling off, so in case anyone else has that issue I think I fixed ours by dragging the tickets back to the left one column and then re-dragging them to done (our rightmost column). Once I did that the little green checkmark that says they're "done" appeared on the card. Hopefully this will mean they'll start rolling off in 14 days. 

Like # people like this
Toni Lahnalampi May 18, 2020

We had the exact same issue, after we migrated our project from classic to next-gen project.

Like # people like this