Our sprints are 3 weeks length, starting on a Tuesday and ending on third week Monday.
Sprint Planning->Week1-> Tuesday - Thursday
Sprint Execution->Week1-Friday-Week 3 Monday
If I put Sprint 1 Tuesday as my 1st day of the sprint then I won't have my sprint backlog ready by week1 Thursday so the burndown chart will look like I added additional scope and it won't reflect the true data. How do I handle the start date in Jira so the burn down reflects the true scope?
See below from the Scrum Guide - you shouldn't be spending 3 days planning! for a 3 week sprint, you should only be spending 3 - 6 hours of the first day planning, then your sprint backlog is complete on the first day and your burndown will be fine.
Why are you spending so much time planning?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.