Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Next challenges

Recent achievements

  • Global
  • Personal

Recognition

  • Give kudos
  • Received
  • Given

Leaderboard

  • Global

Trophy case

Kudos (beta program)

Kudos logo

You've been invited into the Kudos (beta program) private group. Chat with others in the program, or give feedback to Atlassian.

View group

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Is there any report in Jira for iteration planning to see how many hours available capacity team has

Is there any report in Jira for iteration planning to see how many hours each Resource has and how many hours hours are left? I need before the sprint start.

for example- if the below data is there and all the resources has 60 hrs total capacity-

name         sub-task.     Hours consumed

neelam.      coding.        5

jen.              Testing.       4

mahika.       Test plan.    4

mahika.        Defect.       6

neelam.        Testing.      4

jen.                Review.       4

 

report I want-

name.          Total capacity.       Hours consumed

mahika.        60.                          10

neelam.        60.                           9

jen.               60.                           8

2 answers

0 votes
Danny Community Leader Jan 19, 2020

Hello @neelam_annad

Unfortunately, Jira out of the box does not have the concept of a resource's capacity. For this functionality, Atlassian provides Portfolio for Jira in which you can create teams, manage their capacities and plan your future roadmaps. 

You can try the add-on for free for 30 days before committing to it.

If this is not preferred, there are other add-ons that the community has suggested in a previous post.

 

Hope this helps,

Danny 

I am using Portfolio plug-in and Couldn’t able to understand as how plugin calculates capacity. When we do the calculation in excel it works fine but the same in team plan says over burn...no matter if we try with story points or hours

can you help as how Jira portfolio plug-in does the over burn calculation in terms of story points and hours..

 

what should we do to match excel calculation with what team plan says...

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Marketplace Apps & Integrations

Happy New Year and Welcome New Marketplace Partner Program Partners!

Happy New Year! We hope you all had a safe and restful holiday season. 2020 was a unique year full of unforeseen events; however, as we enter the new year of 2021, we’re optimistic for the light at t...

541 views 7 20
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you