Tom Kucharski _SoftwarePlant_ February 7, 2017

Request sent by one of our customers:


Hi,
I am working on the Gnatt chart feature but have a couple of questions that I haven’t been able to figure out on my own. What do the Orange and Grey ribbon indicators mean?
unnamed (1).png

1 answer

1 vote
Tom Kucharski _SoftwarePlant_ February 7, 2017

Hi,

Ok, now I have more information. This is related to deferred tasks - please read more here - https://softwareplant.atlassian.net/wiki/display/BP/Task+operations#Taskoperations-Committingtasks(defferedtasks).

After you re-sync they should change to normal (RR on the keyboard if you have admin privileges) as this is the indication of tasks that needed acceptance.

About the refreshing please use the "E" shortcut to display the edit screen. The refreshing is set to 3 seconds so if it does not update let us know and we will investigate.