I want to create a report that shows work items assigned and completed per assignee per sprint. Even better, we want to show their trend over time. Thoughts?
Thanks
Hi Thomas,
While I'm certain there should be a way to achieve this I think that this is a very bad idea. Because you're using sprints and the term velocity I'm assuming your using an agile methodology.
Agile focusses on the responsibilities as a team, not as an individual. While someone might be helping others all sprint long getting their work done and making sure the sprint goal is reached, he/she won't have any issues assigned to their name and thus it looks like they've performed badly even though they've fulfilled a very important role in that sprint.
Just my 2 cents.
Best,
Maarten
This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.
Read moreAtlas Camp is our developer event which will take place in Barcelona, Spain from the 6th -7th of September . This is a great opportunity to meet other developers and get n...
Connect with like-minded Atlassian users at free events near you!
Find a groupConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no AUG chapters near you at the moment.
Start an AUGYou're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.