Version = Sprint Automatic ?

Leo Nishanth Anthony February 13, 2018

Example: I create issue A, B, C, D ,E and F in sprint 1 and post some days I realize that this won't be delivered in sprint 1 but in sprint 2. Imagine I do the same process issues B, C, D.

As you can see only E & F is delivered in the current sprint and version. 

Performed: I have to manually change the version change to A, B, C and D. 

Expected: When I move the items from sprint to sprint, I would like to have the version also change automatically.

we are in this version JIRA v7.2.8

Thanks in advance for your reply.

2 answers

0 votes
Thomas Schlegel
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 16, 2018

Hi Leo,

the version field has no relation to the sprint. You have to change both, the fields are independent.

0 votes
Leo Nishanth Anthony February 14, 2018

Any suggestion or idea?