Time planned per assignee and per project

We are using the 'plan' feature of the tempo timesheet add-on to 'reserve' time per consultant.
Is there a way to create a report detailing out 'number of days planned per project and per user' ?

 

Francis 

1 answer

Hi Francis,

you can create a report for planned hours on a Project and User by using the Excel export of the Project Timesheet. This export includes a "Planned" tab that shows all hours planned for a user for a day in the Project for the chosen timeperiod. You can then pivot the table to show only the data you are interested in (see also http://blog.tempoplugin.com/2012/pivoting-tempo-and-jira-reports-using-excel/)

Regards,

Susanne

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Bridget Sauer
Published Apr 19, 2018 in Marketplace Apps

Calling all developers––You're invited to Atlas Camp 2018

 Atlas Camp   is our developer event which will take place in Barcelona, Spain  from the 6th -7th of   September . This is a great opportunity to meet other developers and get n...

366 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you