Tempo Planner all people over allocated

Hi,

How come that Tempo Planners shows all people over allocated, even if they don't have any planned items?

image2015-8-28 16:33:9.png

Thanks!

2 answers

Hi Linus,

can you take a look at your Teams. It looks like your users are members in more than one Team and the sum of their availability is more than 100%  

Regards,

Susanne

Hi Susanne

You're absolutely right, when I correct the team assignment it works. Thanks!

Regards, Linus

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Jul 10, 2018 in Marketplace Apps

If you’re an Atlassian app developer, you’ll want to know about Atlas Camp!

This September 6-7, hundreds of Atlassian App developers will flock to Barcelona Spain to build skills, discover product roadmaps, meet face-to-face with the Atlassian team, and learn how to extend t...

177 views 0 4
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you