Hi,

How come that Tempo Planners shows all people over allocated, even if they don't have any planned items?

image2015-8-28 16:33:9.png

Thanks!

2 answers

Hi Linus,

can you take a look at your Teams. It looks like your users are members in more than one Team and the sum of their availability is more than 100%  

Regards,

Susanne

Hi Susanne

You're absolutely right, when I correct the team assignment it works. Thanks!

Regards, Linus

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Mar 13, 2019 in Marketplace Apps

Marketplace Spotlight: Marketing apps for Confluence to keep your teams working on the same page

                                                      &nbsp...

280 views 0 7
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you