Sync duration in past for Joggler

Hi,

As far as I can see, the sync between Jira and Toggler works fine if Task in Joggler is named with Jira-key from beginning.

However, sometimes the key kan only be added some time after the time trakcing in toggle is done, when updating description of tracked time.

Does Joggler sync this changed entry from the past into jira issue? if yes, how long in the past?

kind regards

Christoph

1 answer

1 accepted

0 votes
Accepted answer

Hi Christoph

Joggler does a synch for time entries up to one month back every 5 minutes and one year back every night at 2 o'clock. I assume that should be more then enough.

HTH

Benno

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Oct 31, 2018 in Marketplace Apps

Marketplace Spotlight: Zephyr

Hello Atlassian Community! Each month, we run a series of Spotlights to highlight Marketplace vendors and apps that our team thinks this Community would find valuable. In last month's Spotlig...

300 views 0 1
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you