Problems with Agile Story Map plugin

Hi, I ve installed the plugin and I m having the following problems: - The epic is not summing up the story points of the child storys - Because of this, the progress bar shows nothing - I ve tried to put manually the story points of the Epic, to see if the progress bar would show something, nothing had changed. - When I add a Story on the plus button beside the Epic, a put all the information of the Story. The green square of the sucess message is exhibited, but no message is showed - After this, the Story has not been added

5 answers

Hi Amanda,

let me just explain how the progress bar works:

the epic itself has a own editable story point field.
The sum of the related stories is shown at the progress bar's mouse over message.
the progress bar shows the relation between stories in status resolved or closed and all other status.

what JIRA/Greenhopper Version do you use?

Hi Florian.

"The sum of the related stories is shown at the progress bar's mouse over message.
the progress bar shows the relation between stories in status resolved or closed and all other status."

Not on my installation. I ve tried everything but nothing seems to work. I ve put story points in the epics, stories, closed, resolved stories, but nothing happens (the progress bar still shows 0%).

Talking about the implementation itself, the epic should be the sum of its story child. What if the sum of the story is greater than the value in the epic? But I couldn t test this :(

I m thinking this plugin is still very buggy. Its slow, when I create the epic the epic is not shown, the same happens to the stories. The confirmation messages come empty. Too weird.

My versions

Atlassian GreenHopper (v6.1.3.2)
Atlassian JIRA (v5.2.5)

Hi Amanda,

hm, I am not able to reproduce the behavior that you has been described.

Do you use a particular workflow configuration with your own staus?

If you want we can do a webex session together - to do so please contact me via the vendors email address, than we can arrange an appointment.

Florian

@Florian Bauer, I really would like to have an webex session. I m still having problems with the evaluation license. Even with Jira 6

Our progress bar shows a percentage and in brackets a count of stories points complete out of total story points.

However, the Epic is only calculting stories not other issues type that have story points (in fact, those issue types are not even shown at all - there is no filter to control by issue type).

-Johnny

Hey I am facing the same issue. Does any one know the solution?

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Tuesday in Marketplace Apps

If you’re an Atlassian app developer, you’ll want to know about Atlas Camp!

This September 6-7, hundreds of Atlassian App developers will flock to Barcelona Spain to build skills, discover product roadmaps, meet face-to-face with the Atlassian team, and learn how to extend t...

119 views 0 4
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you