When we started evaluating Jira, we install "JIRA Gantt-Chart Plugin" and then "JIRA Gantt-Chart Project", leaving both working simultaneously.
The JIRA Gantt-Chart Plugin created the custom fields "Planned Start" and "Planned End", which were set respectively as "Start Time" and "End Time" at JIRA Gantt Chart Project. We entered several projects and issues... Later uninstall the JIRA Gantt-Chart Plugin, which did not eliminate the custom fields created by it. Then we configure the "Start Time" and "End Time" of the JIRA Gantt Chart Project to not use custom fields (set to empty) and then try to eliminate the custom fields "Start Time" and "End Time", but a System Error occurred, cause: java.lang.NullPointerException.
What actions should we perform in order that the database does not have inconsistencies and the JIRA Gantt Chart Project continues to operate with default options (without the use of "Start Time" and "End Time")?.
What is the stack trace?
In general, once you have reconfigured the custom field, JIRA Gantt Chart Project can work using the default fields of issues. The delete of custom fields is not necessary.
For further questions and issue, please use this service:
https://studio.plugins.atlassian.com/browse/JRAGANTT
Best regards
Yves YANG