New tickets are not included in Gantt Chart

I installed the Gantt plug in and clicked on the Generate planning dates for issues having no start/end date. All the tickets in the project are now displaying in the Gantt Chart.

After that I added 20+ more tickets, which none of them are showing in the Gantt Chart. I have rescheduling is enabled on the project. I also clicked the button Generate planning dates again, but the tickets still do not show.

What do I need to do to get these tickets to display?

2 answers

Without planning dates (start/end) issues are not displayed on Gantt-Chart. Planning dates are pre-calculated if you specify original estimation while you create an issue. Please read embedded documentation (main gantt configuration, tab "re-scheduling").

Separate email track has been used to follow up ...

Frank was very attentive and assisted me in getting this issue resloved. Thanks Frank!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Mar 13, 2019 in Marketplace Apps

Marketplace Spotlight: Marketing apps for Confluence to keep your teams working on the same page

                                                      &nbsp...

236 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you