Issues that are completed late in Gantt-Chart

Hi,

I am evaluating the Gantt-Chart and I have a question;

How do you have to configure to see the issues, for example in red, that were completed later than planned end date in Gantt Chart? So that for example in the end you could see directly from Gantt how many issues were completed late?

I tried logging in work later than planned end date, but I could not get it to show in Gantt in any special way.

1 answer

What you can do is using base-lining together with my free JIRA-addon "traffic-light": in that case, the traffic-light customfield will be set to red if end date differs from baseline-end more than 20%, yellow in case of > 10% else green.

Regards,
Frank

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Wednesday in Marketplace Apps

Marketplace Spotlight: Marketing apps for Confluence to keep your teams working on the same page

                                                      &nbsp...

120 views 0 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you