In JIRA, a sprint's Velocity Chart report lists two categories of issues complete: Completed Issues, and Issues Completed Outside of Sprint. eazyBI counts all of these in its Story Points Resolved calculated measure. Is there a way to create a calculated measure that excludes the Issues Completed Outside of a Sprint?

Thank you.

-Ryan

2 answers

0 votes
Ryan April 7, 2016

Hi, Lauma. When you click on one of the sprint names at the bottom of the velocity chart, it shows you the issues committed and completed during that sprint. That's where the Issues Completed Outside of Sprint appears. This answer explains what constitutes Issues Completed Outside of Sprint.

I've attached a screenshot:

Velocity Chart JIRA.jpg

0 votes
Lauma Cīrule
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 7, 2016

Hi Ryan,

I checked JIRA Velocity chart and it has only Story points Committed and Completed. This is similar to this example report in eazyBI

How would you define the Story points completed outside Sprint? Are those part of resolved story points that are completed after Sprint end date?

Kind regards,
Lauma / support@eazybi.com 