Hello Lilach,

 

Thank you for your inquiry.

For the moment, the only way to keep track of such changes being made, is to create a baseline on the Gantt chart - WBS section. This can be done by clicking a 'cog' icon on the far right Work Breakdown Structure column and selecting Baselines - Create Baseline. Then in View option 'Show' Columns and Baselines. This way, any time an epic or any other issue has been moved (updated) from one cadence to another, the baseline will mark an original location of the issue on the Gantt chart. 

Please let us know if this resolution works for you and if you have any other question don't hesitate to drop an e-mail to: support@softwareplant.com 

 

Kind Regards,

Piotr of SoftwarePlant Support

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Aug 22, 2018 in Marketplace Apps

How a Marketplace app tech team is achieving gender diversity

Hello! My name is Genevieve Blanch, and I'm the Marketing Manager at RefinedWiki, creators of apps to give teams the tools to customize Atlassian platforms. Currently, 44% of the tech team at Re...

536 views 3 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you