Incorrect progress bar updates when logging time over the weekend

Jan Croker February 19, 2013

I think there is a problem with the 'logged work' indicators on a GANTT bar, when the logged work extends over a weekend (without weekend working).

e.g I created an issue (sub-task type):

13 day duration , starting today (20th Feb to 8th march).

Logged work = 10days ---> the progress bar is only showing 9 days.

Is this a known problem.?

I can attach screen shots if needed.

Thanks,

jan

2 answers

1 accepted

0 votes
Answer accepted
Frank Polscheit
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 25, 2013

Hi Jan,
sorry for waiting a bit, but I was looking on the screenshots you have provided and could not find any problem for quite some time. But now, I get it: it's a conceptual mis-understanding and the Gantt-Chart plugin works fine as designed.

The progress bar graphically represents the percentual progress of an issue over the full length of its gantt-bar: 77% in your screenshots (10 logged working days / 13 estimated working days = 77%). The number of pixel being colored as progress bar to reflect this 77% of calendar days including weekends look like graphically almost identical to the duration of 9 working days, but this has no semantical relationship!

Regards,
Frank

Jan Croker February 25, 2013

Ok Frank, thank-you.

0 votes
Frank Polscheit
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 19, 2013

Yes, please attach a sample screenshot and what Gantt-Chart version you are using.

Jan Croker February 19, 2013

Hi Frank,

Is there a bettre way to do this? - Sorry the images are a bit big! Hope you can see them ok. One is the resultant display the second is the Work Log from the Gantt bar.

Gantt Chart plugin version is

Version:2.2-JIRA5.2-UPM2.8.1

Work log:










Jan Croker February 24, 2013

Hi Frank,

Have you managed to see bug with 'logging time over the weekend'? Any progress?

thanks,