How to change Tempo timesheet period from monthly to weekly

Is there a way to change the period range in Tempo timesheet? In fact, in my organization we use to check the work weekly instead of monthly. By default in Tempo, the work can be submitted only monthly.

So now I would like to know If I can change this to set it to a weekly management including period and submission management ?

Thank you in advance

2 answers

Hi Badi,

it is not possible to change the period range in Tempo Timesheets, but the Timesheet Approval can be done monthly (by period) or weekly.

To change this setting, go to Tempo Administration, Global Configuration and change the "Configure timesheet approval process" to weekly. Please take also a look at https://tempoplugin.jira.com/wiki/display/TEMPO/Timesheet+Approval+Process for more information.

Regards,

Susanne

Hi,

I can't see this parameter since the last update, I use the 1.1.36-AC version:

Captura de pantalla 2017-05-24 a las 13.09.32.png

 

Where can I chenge this param?

Thanks,
Christian Heine

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Bridget Sauer
Published Thursday in Marketplace Apps

Calling all developers––You're invited to Atlas Camp 2018

 Atlas Camp   is our developer event which will take place in Barcelona, Spain  from the 6th -7th of   September . This is a great opportunity to meet other developers and get n...

366 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you