How does the custom field "Gantt-Chart" works

Hi,

after installing the Gantt Chat plugin there is a custom field available called "Gantt Bar". From the field description I assume it presents the gantt bar from the gantt chart on my issue screen. If so, that would be very helpful for status tracking. However, the field seems not to work. I can´t enter a field value (actually the field isnt even shown in my edit mask). What do I have to do to mark that field work in the intended way?

Kind regards

Frank

PS.: We use the latest version of the plugin 

2 answers

That customfield has been introduced by Gantt-Chart v2.x to display a Gantt-Chart integrated within JIRA's Issue Navigator (search result). Based on the Atlassian changes (various views like detail view and list view), that functionality does no longer work: to indicate that, a "n.a" (not applicable) is displayed as column content. Instead, you have an additional project tab panel "Gantt-Chart" to display that information with a lot of user configurable look & feel.

Per issue, I recommend to put the customfields "planned start", "planned end", "baseline start", "baseline end" and "Gantt Options" on the edit- and view-screen. If you modify them, any Gantt chart will be displayed accordingly if you have enabled re-scheduling.

Kind regards,
Frank

PS.: if you are located within Germany/Europe, we can have phone talk to clarify that or other questions shortly.

Thanks for the fast response. Yes, I am located in Frankfurt. How can I contact you?

You can send me your contact details via email at frank.oestreich@hauck-aufhaeuser.de too.

kind regards

Frank

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Mar 13, 2019 in Marketplace Apps

Marketplace Spotlight: Marketing apps for Confluence to keep your teams working on the same page

                                                      &nbsp...

275 views 0 7
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you