Gantt Chart plugin: Project Resource Planning view - calculations on the project bar

I wonder if you could explain what the numbers (in hours) indicate on the project line within the Gantt Chart?

1 answer

1 accepted

0 votes
Answer accepted

Hi Jan,

having updated to v2.2.2+ of my Gantt-Chart, the numbers illustrate average working hours as explained on the graphic below.

Kind regards,
Frank

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Mar 13, 2019 in Marketplace Apps

Marketplace Spotlight: Marketing apps for Confluence to keep your teams working on the same page

                                                      &nbsp...

245 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you