Change load on ressource per day

Hello, 

 

I'm new with JIRA tools, especially with the Big Picture Entreprise plug-in. I'm pretty entousiast in front of all possibilities nevertheless I don't know how to change the load off one issue. 

For exemple, this is my ressource view : 

Capture du 2017-06-08 10-38-50.png

This worker have two task on the same day so he is loaded at 16h / day. But that's not the reality. How can I configure each issue to take only 1h / day for exemple ?

 

Thanks in advance for your time, 

Best regards, 

1 answer

This widget could not be displayed.

Hello Thomas,

 

Thank you for your query.

At the moment BigPicture's Resource module allows user to set and to distribute a workload per resource / per day, though as we understand growing needs of our clients, we would like to add a feature which would also allow us to distribute such a workload per task / per resource / per day. This functionality is not yet available though, we are planning to implement it by the end of this year.

https://softwareplant.com/jira/browse/PPM-9

 

Kind Regards,

Piotr of SP Support

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Aug 22, 2018 in Marketplace Apps

How a Marketplace app tech team is achieving gender diversity

Hello! My name is Genevieve Blanch, and I'm the Marketing Manager at RefinedWiki, creators of apps to give teams the tools to customize Atlassian platforms. Currently, 44% of the tech team at Re...

509 views 3 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you