Sometimes a task need to be assigned to more than one assignee, and the date duration for them may be different, currently I can only add one assignee and use resource unit to control it, how should I add more than one assignee? I tried Group assignee in Jira software, but it didn't works in WBS Gantt, please help, thank you
Hi,
Assignee is the system field in Jira; it is designed one user per a issue. So, regardless WBS Gantt Chart, the restriction impacts to whole Jira. Surely, making customfield as 'group assignee' by group picker is workaround but fundamentally, different from original assignee field. See more.. below link.
If you have any questions about WBS Gantt-Chart. feel free to contact WBS Gantt-Chart Support.