BigPicture markers/milestones Edited

How can I create my own markers or milestones in BigPicture?

Thanks, Rafi

1 answer

For vertical lines on the Gantt:

On the Gantt portion of the Program (so NOT on the WBS side) click on the date on the timeline and a Marker dialog box will open.  Make sure you have View-->Show Markers turned on.  Bad thing is that they are only visible to you.  If you have other users of the same program they won't see the markers you've created.  kind of a bummer.

 

for Milestone tasks:

click on the WBS task, click on the ellipse, change Task Type to milestone (everyone sees those)

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 30, 2018 in Marketplace Apps

Three tips for boosting your board's efficiency with Story Maps

Trello is one of the most effective tools for driving your sprints. It's customizable for every Agile team and product owners and Scrum masters (SM) love it. However, Agile teams often struggle with:...

863 views 2 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you