I am wondering if it is possible to “lock” an issue in the Gantt time-line. This would be very valueable for us. When two issues are connected the “source” issue can now move the “destination” issue without any notification. This can cause big problems for us.
Best regards,
Francois Pierrot
Team Leader Applications
CES & General R&D
When issues are linked together, by default the auto-scheduling mechanism indeed can move them on the timeline to make them match their issue link type. However, you can turn this off easily by clicking the main cog icon on the Gantt (upper-right corner of Columns).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.