BigPicture lock issue to gantt

Francois Pierrot January 28, 2016

I am wondering if it is possible to “lock” an issue in the Gantt time-line. This would be very valueable for us. When two issues are connected the “source” issue can now move the “destination” issue without any notification. This can cause big problems for us.

 

Best regards,

Francois Pierrot

Team Leader Applications

CES & General R&D

1 answer

0 votes
Matthew Jagiello
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 28, 2016
Hi,

When issues are linked together, by default the auto-scheduling mechanism indeed can move them on the timeline to make them match their issue link type. However, you can turn this off easily by clicking the main cog icon on the Gantt (upper-right corner of Columns).