BigPicture lock issue to gantt

I am wondering if it is possible to “lock” an issue in the Gantt time-line. This would be very valueable for us. When two issues are connected the “source” issue can now move the “destination” issue without any notification. This can cause big problems for us.

 

Best regards,

Francois Pierrot

Team Leader Applications

CES & General R&D

1 answer

Hi,

When issues are linked together, by default the auto-scheduling mechanism indeed can move them on the timeline to make them match their issue link type. However, you can turn this off easily by clicking the main cog icon on the Gantt (upper-right corner of Columns).

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Oct 31, 2018 in Marketplace Apps

Marketplace Spotlight: Zephyr

Hello Atlassian Community! Each month, we run a series of Spotlights to highlight Marketplace vendors and apps that our team thinks this Community would find valuable. In last month's Spotlig...

412 views 0 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you