Hello
I would like to know if it is possible to get an automatic report on planned x actual schedule - graphical and text, if possible. I am not especially interested on time schedules, but on project schedule and completion within deadlines. My goals would be comparison and announcement of meeting milestones, completed tasks, etc. I am trying Intelligent Reports, and would be delighted to join both features.
My apologies if there is already an answer, I could not find it.
Thanks
Hi Leontina,
you can specify milestone task and dependencies between prior task and that milestones. Shifting issue's end date into the future result in updating/re-scheduling of all dependent issues including the milestones. You can report on the planned end date for example.
The aggregated progresses are visible within my Gantt-Chart as well.
Automatic reports like you are interested in, is not available yet.
Regards,
Frank
Hi Frank,
Thank you so much for your prompt response. I see that those things are visible, but my client demands a gantt chart on the weekly report.
Maybe on a future version...
Thanks again