Assign Group of Sub-task to a specific Task

Benny September 5, 2018

Is there a way to to automatically add a group of sub-task to a task when it is created. The sub-task do not have to be assigned to an individual just created.

Example: The Task is created by the user and the sub-task are automatically assigned

Task = Book

  • Sub-task = Typeset
  • Sub-task = Edit
  • Sub-task = Send to Printer

    

1 answer

1 accepted

1 vote
Answer accepted
Tansu Akdeniz
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 6, 2018

Hi @Benny,

You can automatically create group of sub-tasks when issue is created. But this feature doesn't come out-of-box.

There are lots of "create subtask" post-functions that comes via some add-ons on marketplace such as Script Runner, Automation, JMWE etc.

Please take a look at the marketplace.

Benny September 6, 2018

I have Script Runner, but I cannot find a example of how to create a sub-task when a task that has an issue type of Book is created.

Tansu Akdeniz
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 6, 2018
  • Go to the related workflow and edit
  • Find Create transition and click to post-functions
  • Add a new post-function
  • Select Script post-functions than "Create Subtask"
  • Add a condition by using examples (issue type of Book)
  • Finalize the configuration.

Hope this helps.

Benny September 6, 2018

Thanks Tansu. This help a lot!!!!!!