Hello,
we installed a trial version of bigpicture and have couple of basic questions.
1) in my advanced fields i couldn't find "links" tab to be as my column. how can i modify this?
image2016-3-9 11:39:44.png
2) resource allocation. how can i set "user A" to work on issue "#2" 4 hours and "user A" to work on issue "#3" 2 hours for the specific day.
Thanks
Hi,
Just as an exmaple, a task starting on the 1st, ending on the 11th has 10 days of duration. With 100 hours of original estimate, it will be 10 hours of work each day.
Thanks Matthew,
and another question if you can please.
Can I automatically set Start Date when Issue Status is changed to "In Progress" ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Currently not, ie status does not affect the start date. However, if you add an issue without its start date specified, it will take the position of the create's date, and issues in different statuses are color-coded.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Happy New Year! We hope you all had a safe and restful holiday season. 2020 was a unique year full of unforeseen events; however, as we enter the new year of 2021, we’re optimistic for the light at t...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.