Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,467,388
Community Members
 
Community Events
177
Community Groups

Update Original Estimate using Automatic rules

Hi,

 

I am using Jira Cloud, and I want to update the original Estimate days according to Story points number. For example, if the user will enter 8 story points for a story, I would like to update the Original estimate to 8d. 

I know how to set the trigger, but failing in the Original Estimate update.

Any advise will be great.

 

Thanks,

Itamar

2 answers

1 accepted

Hi @Gaurav 

 

This is what I did, but with no success. The rule is triggered when changing story point for a story, but the Original Estimate field is not updated.

 

A screenshot of the rule is attached:

 

6768.jpg

 

Tired this code in several forms but nothing helps.

 

Please advise what is wrong with my code.

Gaurav Community Leader Aug 05, 2021

Hello @Itamar 

The reason for the Original Estimate not updating is the condition used in the Branch. It states if this is triggered from an Epic, then update/ take action on all issues in the Epic. BUt we are triggering/ updating a story, so it does not work. Refer to the first screenshot.

If I understand your use case, you need to update the Original Estimate any time the Story Points are updated. Based on this understanding, the rule can be simply created using smart values. Please confirm this understanding. Refer to the second screenshot.

Alternatively, it could be that with the change of Epic Story POints, you wish to update the estimates for every issue of that Epic. Even this is possible with automation. Refer to the third screenshot.

Please find below the screenshots, for all these options.

Please accept the answer if this helps solve your query else respond and allow others to share input.

Story update from Epic.jpgStory update.JPGStory update from Epic 1.JPG

Hi @Gaurav

 

Thanks a lot! your first suggestion was exactly what I was trying to do. Updating the specific story that it's story points have been changed.

 

Thanks a lot,

 

Itamar

0 votes
Gaurav Community Leader Aug 04, 2021

Hello @Itamar 

This can be done using automation in Jira. Please find attached the screenshot for the implementation. The rule can be extended and customized as per your requirements.

Please accept the answer if this helps solve your query else respond and allow others to share input.

Original estimate automation.JPG

Suggest an answer