Can we track the % of goal for KR/Objective by linked sub-tasks?
Example: I have a Story called "Enable SSO", with a Task called "Implement OneLogin" - with subtasks under that. When 50% of the subtasks are complete, the Task should be at 50% as well - which when I tie that task to a KR, should also show as 50%, however it still shows as 0%.
Is this working as intended?
Hello @Jay Vlavianos
Currently, this approach we use only for Epic-Jira issue connection to calculate grade based on number of resolved issue connected to Epic.
We would like to implement this feature for Jira issue-Sub-task connection in future.
Best,
Viktor