Time Tracking shows wrong value in the "Logged" section

Johannes Becker Jan 09, 2015

Under "Work Log" there are two entries from two persons showing both "5 hours", the "Logged" bar shows "1d 2h". Seems like somehow the Logged-Bar gets the accumulated value from all "Time spent" entries triggered from Toggl. Can you reproduce this? Do we have something wrong configured?

Thanks for a great plugin!

1 answer

0 votes
Benno Baumgartner Jan 11, 2015

Hi Johannes

The logged bar shows the sum of all the time entries. In your case 5h + 5h = 10h. On the JIRA time tracking configuration page you can define how long a workday is. In your case apparently 8 hours (the default). 1d 2h = 8h + 2h = 10h.

Regards

Benno

 

Suggest an answer

Log in or Sign up to answer
This widget could not be displayed.
This widget could not be displayed.
Community showcase
Posted in Marketplace Apps & Integrations

Demo Den Ep. 4: Continuous Integration with CircleCI & Jira Software

Get ready! Demo Den Episode 4 is coming your way on Tuesday, May 28, 2018 with a Continuous Integration and Delivery special demo. CircleCI Director of Solutions Engineering, Eddie Webb will show us ...

707 views 0 4
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you