Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Next challenges

Recent achievements

  • Global
  • Personal

Recognition

  • Give kudos
  • Received
  • Given

Leaderboard

  • Global

Trophy case

Kudos (beta program)

Kudos logo

You've been invited into the Kudos (beta program) private group. Chat with others in the program, or give feedback to Atlassian.

View group

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Structure Gantt - setting the end date Edited

What is the logic behind the start and end date when scheduling manually?
I got this setting

2020-04-13_12-05-31 (1).png

 

 

Whenever I move the task, the begin date is set (on the issue), but not the end date.

Under what conditions is the end date filled?

1 answer

Hi Francis,

The logic is as follows:

1. When none of the dates are filled, start date is being filled. Duration is calculated based on estimates

2. When start date is filled, it is the only date changed when issue is moved. Duration is calculated based on estimates.

3. When end date is filled, then it is the only changing date. Duration is calculated based on estimates.

4. If both dates are filled both dates change when the issue is moved, but duration is now based on the difference between these two dates.

Please, let me know if it answers your question.

Regards,
Egor Tasa

ALM Works

Hi @Egor Tasa _ALM Works_ 

 

End date needs to be added by the user.  Structure Gantt will only modify is if filled in?

Hi Francis,

That is correct, only start date would be filled automatically.

Regards,
Egor

Is there a condition where the end-date is filled by structure?

Hi Francis,

No, end date is only updated by Structure, but it has to be filled by the user.

Regards,
Egor

Hi @Egor Tasa _ALM Works_ 

 

With the risk of being considered as a noob for the rest of my earthly life, I'm confused about your answer

 

No, end date is only updated by Structure, but it has to be filled by the user

end date is only updated by Structure

and

it has to be filled by the user.

 

Seems to contradict each other.  Is Structure updating the date, or must it be filled by the user.  I think the latter - but a clarification will help

Hi Francis,

Sorry, I have formulated it in a confusing matter. By update I mean change here, that is Structure will not fill the empty end date field, but it will change its value when there is a value already.

Regards,
Egor

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Marketplace Apps & Integrations

Bitbucket Smart Commits vs. Genius Commits - What's the difference?

If you already heard about Smart Commits in Bitbucket, know that you just stumbled upon something even better (and smarter!): Genius Commits by Better DevOps Automation for Jira Data Center (+ Server...

114 views 0 2
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you