Structure.Gantt - Progress bar and percentage

hans rhubesch Govind August 18, 2020

Hello,

The progress bar on the task does not appear when I clicked on the "Progress" under "Gantt Chart Details" found on the top right of the Gantt.

Also when I clicked the task, the Progress % is set to 0 and does not reflect the value found in the grid.

Can someone help me to solve this issue?

 

Thanks

Hans

1 answer

0 votes
David Niro
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
August 20, 2020

Hello Hans,

David from ALM Works here!

From what you describe, it sounds like the Work Estimates and Progress Calculation settings for your Gantt chart may not be aligned with what you are using to track progress.

I would review these two settings to start.
You can find the Work Estimate & Progress Calculation settings by opening:

Gantt chart Settings (gear icon top left gantt window) > Edit Configuration > Scheduling

From here, you can check what is being used in your Work Estimates and Progress Calculation.  By default, the Progress Calculation should be set to “Based on Work Estimate”.

If you do not see any discrepancies here, our support team would be happy to assist you further.  You can reach us via support@almworks.com.

Best,
David

hans rhubesch Govind September 8, 2020

Hello David,

The solution you gave, worked.

 

Thanks a lot

Hans

Like David Niro likes this