As a manager I want to see a report that lists all tasks that are past due - how do I generate such a report?

1 answer

0 votes
All-In-One Support
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 5, 2016

Hello!

To create such report, please follow these steps:

  1. Select List report tab
  2. Add Issue Key, Summary and Description fields from Dimensions
  3. Select JQL Filter
  4. Type or Copy and Paste this JQL in the box: 
    issuetype = Task and duedate < now() and status in (Open, "In Progress")

Click Run.

Please let us know if you face any issues.