JIRA with financial, Project cost reporting

steve.hurley December 11, 2019

Good afternoon all, we are starting to evaluate JIRA but want to also encompass the financials related to the project, so far we have downloaded JIRA (Cloud) and TEMPO TIMESHEETS, what else do we need to facilitate the financial aspect, hope this makes sense.

 

 

 

1 answer

0 votes
carolyn french
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 17, 2019

Hi Steve and welcome!

There is a new Tempo product being developed to track project cost called Tempo Cost Tracker (for cloud). If you're interested in participating in a closed beta program, you can sign up on the website here:

https://www.tempo.io/cost-tracker

Carolyn

steve.hurley December 18, 2019

Not at this stage really, we were informed that TEMPO TIMESHEETS provides financials in relation to time spent by developer against cost of developer by project/sprint is that right, finding it difficult to get a definitive answer on what it we need to cover the financials to be honest, any help appreciated.

carolyn french
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 20, 2019

Sure thing, I'm happy to try to help. What exactly are you looking to track for financials?

Tempo Timesheets Server does provide account management for time spent by developer against cost of developer, but not Cloud. With Cloud Timesheets, you can track how many hours are budgeted against actual, but not the money. See documentation here: https://tempo-io.atlassian.net/wiki/spaces/THC/pages/450691482/Managing+Revenue+and+Billing+-+Tempo+Server

steve.hurley December 22, 2019

Hi Carolyn, merry Xmas, we currently have JIRA Cloud based and Tempo Time sheets but as you say we have no financials with Cloud, so what add on do we need to be able to provide us with a cost breakdown of the Project.