Is it possible to alter a sprint that is attached to an increment in Easy Agile?

Yao Chan June 18, 2020

We made an increment in Easy Agile and 1 team linked the wrong sprints to the increment. Is it possible to attach the right sprints to the increment without having to delete the whole increment?

1 answer

1 accepted

0 votes
Answer accepted
matt.seddon June 18, 2020

Hi Yao,

Thanks for reaching out.

It's not currently possible to edit Sprints synced with a Program today. We do have a story on our backlog to enable this functionality and I have made sure to add your vote to that story.

The good news is that I do have a workaround for you:

You are able to remove and then re-add the affected Team boards from the Program via the 'Edit Program' button on the Increment Overview page.

Once you have re-added those teams, go to each of their Team Planning Boards where you will be asked to configure the Sprints for the board.

You can then map your desired Sprints from the Team's backlog and the Program Increment.

Please reach out if you need any more assistance.

Thanks and have a great day,

Matt

Yao Chan June 24, 2020

Thanks for the reply! Works for now :)

matt.seddon June 24, 2020

No problem.

Feel free to reach out with more questions in future. You can contact us via support@easyagile.com. 

Thanks,

Matt