Import from Jira to MS Project a Board with many epics only one Epic and the tasks

Matium April 6, 2020

I want to import from Jira to MS Project a Board with many epics but only import one Epic and the tasks within that Epic. 

2 answers

1 accepted

0 votes
Answer accepted
Sergey Gussak
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 8, 2020

Deleted

0 votes
Sergey Gussak
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 6, 2020

With Ceptah Bridge, you can import issues from JIRA to MS Project using a JQL query that yields the desired Epic with its tasks. Also, you can configure Ceptah Bridge to place the tasks under the Epic in MS Project.

Matium April 6, 2020

I have tried to use ceptah bridge but how do I tell it to import the tasks, also not familiar with jql query. The epic import but not the tasks.

Sergey Gussak
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 8, 2020

To import an Epic with all its tasks, enter the following in the JQL field when importing:

Key=PK-1 OR "Epic Link" = PK-1

(replace PK-1 with the issue key of your Epic)

Matium April 15, 2020

thank you

Suggest an answer

Log in or Sign up to answer