How to use Jira Automation to move issue from Future Sprint to another Future Sprint....

Dave Mitchell February 2, 2024

Seems simple, but I can't find an answer or figure it out.... 

How do I setup a Jira Automation rule that will change the Sprint of an issue, from one Future Sprint, to another Future Sprint (both are known names), based on a change in the Story Points field.

 

 

1 answer

1 accepted

0 votes
Answer accepted
Kseniia Trushnikova
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 6, 2024

Hey @Dave Mitchell,

Maybe this will work?

Screenshot 2024-02-06 at 11.53.01.png

Dave Mitchell February 6, 2024

Yes; beautiful......Thanks for working that up for me.... Learning all the time....

Dave Mitchell February 6, 2024

Works just as expected!

Dave Mitchell February 6, 2024

We added another condition to check for value of "Story Points" (we use larger values to signal more decomposition is needed), but this is really helpful; got "pointed" in the right direction. (giggle).