How to sum subtasks estimations to parent task automatically?

Pooja June 3, 2020

For Example.

  1. Story A has 3 subtasks,
  • Subtask 1 - 2 hours
  • Subtask 2- 3 hours
  • subtasks 3- 1 hour

So Story A = 6 Hours.

Parent Original Estimation field should get updated automatically once we update the Original estimation field of subtasks. How can we make it possible with the automation of the jira plugin?

2 answers

2 votes
Ricardo Jacamo March 29, 2022

Hi Pooja,

Were you able to configure an automation script to have story-level issues' time estimates equal the sums of their sub-tasks' time estimates? Unfortunately, the post shared by John appears to address story-point-based estimation only.

Iris Gal June 7, 2022

Hi Ricardo
I an interested in this as well - have you found something?

0 votes
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 3, 2020

Suggest an answer

Log in or Sign up to answer