How to set a task beginning and end date in BigPicture outside of the Gantt view?

Jorge Blanco Jan 04, 2018

I have a task that got a random start date somehow way in the future and it's a pain to move it manually in the gantt chart. Where else can I change the start/end date for this task?

(I'm using the default settings for Big Picture)

1 answer

0 votes
Ericka Samuels Jan 04, 2018

if you've added the start and end date fields to the JIRA screen and issue type screen scheme then you can edit those fields right from the JIRA view/edit issue screen.

Suggest an answer

Log in or Sign up to answer
This widget could not be displayed.
This widget could not be displayed.
Community showcase
Posted in Marketplace Apps & Integrations

Demo Den Ep. 4: Continuous Integration with CircleCI & Jira Software

Get ready! Demo Den Episode 4 is coming your way on Tuesday, May 28, 2018 with a Continuous Integration and Delivery special demo. CircleCI Director of Solutions Engineering, Eddie Webb will show us ...

709 views 0 4
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you