Hi community,
We are planning our work in Activity Timeline. When we schedule the issues with estimates the Estimate Panel shows the hours distributed equally between the days.
For example, we have task from Monday to Tuesday estimated in 10 hours. The estimate is splitted 5 hours for Monday and 5 hours for Tuesday.
I need 8 hours for Monday and 2 hours for Tuesday. Is it possible to make? Any suggestion?
Thank you
ActivityTimeline has 2 Workload Calculation Modes: Liquide (that you currently using) and Balanced. To change the modes you need go to Configuration -> Workload Calculation Algorithm -> Select "Balance Mode" -> Click "Update"