Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,456,145
Community Members
 
Community Events
176
Community Groups

EVM based on a single issue?

Hi there,

We are evaluating Folio to handle our EVM reporting (currently a labor intensive query/excel process). Our integrations between our current system and JIRA limit us to 1 issue per project. When we log time to a project, we also indicate a completion percent or estimate to completion. Is it possible to set Folio up in a similar way where the EVM are based on the Remaining Effort and Original Estimate for a single issue rather than the completion state of multiple issues?

Thanks,

-Rick

3 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Answer accepted

Hi Richard,

In FOLIO 5.1 we have introduced the progressively earned value. I am pretty sure that it will nicely answer your need :)

The "progressively earned value" allows you to get credited for earned value on issues proportionally to their degree of completion. This degree of completion for an issue is computed as follow:

Degree of completion = Total Time Spent / ( Total time spent + Remaining Estiomate)

So the partial earned value of the issue is then

Partial Earned Value = Original Estimate * Degree of completion

By default, FOLIO does not use progressively earned value. This setting can be set in the folio's configuration under the "Earning Rule' section. You can set your folio to apply the progressively earned value to all issues or only on a specific set of issues based on a label set.


So in your case you would have a folio where the scope is the 1 issue of the project.
The folio would have its "progressively earned value" rule set to all issues.

Let me know if this answers your need or not :)

Cheers,
JC

Score!

This must have been a recent release, I just installed Folio last week. The Progressive Earned Value option is exactly what I needed!

Thanks,

-Rick

The timing was actually good...
FOLIO 5.1 was released last night :)

Cheers
JC

Hi Richard, I would also recommend this app for seeing EVM at the issue-level: 

 Aneto Project Accounting System with Earned Value Management 

 

Josh

Aneto

0 votes

You can also check FOLIO's documentation for all details about Progressive Earned Value and how it is calculated.