EVM based on a single issue?

Hi there,

We are evaluating Folio to handle our EVM reporting (currently a labor intensive query/excel process). Our integrations between our current system and JIRA limit us to 1 issue per project. When we log time to a project, we also indicate a completion percent or estimate to completion. Is it possible to set Folio up in a similar way where the EVM are based on the Remaining Effort and Original Estimate for a single issue rather than the completion state of multiple issues?

Thanks,

-Rick

3 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Answer accepted

Hi Richard,

In FOLIO 5.1 we have introduced the progressively earned value. I am pretty sure that it will nicely answer your need :)

The "progressively earned value" allows you to get credited for earned value on issues proportionally to their degree of completion. This degree of completion for an issue is computed as follow:

Degree of completion = Total Time Spent / ( Total time spent + Remaining Estiomate)

So the partial earned value of the issue is then

Partial Earned Value = Original Estimate * Degree of completion

By default, FOLIO does not use progressively earned value. This setting can be set in the folio's configuration under the "Earning Rule' section. You can set your folio to apply the progressively earned value to all issues or only on a specific set of issues based on a label set.


So in your case you would have a folio where the scope is the 1 issue of the project.
The folio would have its "progressively earned value" rule set to all issues.

Let me know if this answers your need or not :)

Cheers,
JC

Score!

This must have been a recent release, I just installed Folio last week. The Progressive Earned Value option is exactly what I needed!

Thanks,

-Rick

The timing was actually good...
FOLIO 5.1 was released last night :)

Cheers
JC

You can also check FOLIO's documentation for all details about Progressive Earned Value and how it is calculated.

Hi Richard, I would also recommend this app for seeing EVM at the issue-level: 

 Aneto Project Accounting System with Earned Value Management 

 

Josh

Aneto

TAGS
Community showcase
Published in Marketplace Apps & Integrations

🤺 Atlympic Event: Partnerships

Hello Community!  Quick disclaimer: We are running a contest on Community (The Atlympics!) from July 23rd - August 8th of 2021. If you are interested in participating in this contest (prizes! ...

149 views 2 6
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you