Disable auto-sync between JIra and BigGantt

Don Salz September 20, 2019

When a change is made in BIgGantt, say linking two issues, the change is immediately reflected in Jira. Is there a way to disable that, and only sync manually? I have tried turning off all the synchronizers in BigGantt, but that didn't do the trick.

1 answer

0 votes
Patryk-SoftwarePlant
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 3, 2020

Hi Don,

When it comes to the issue links, you can only disable synchronization between Gantt and Jira links. Synchronizing links back will not update the previously created links when synchronization was disabled.

Here is the view of the Link configuration with switched off synchronization:

link_conf_off.png

Screenshot taken from BigPicture v.7.11.16 for Jira Server.

Let me know if you need more information.

Cheers,

Patryk