You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hello! I tried to search for my problem, but couldnt find any solutions.
How can I move the whole line of epics by just pulling one epic to another date in case it's linked? Just like you can do on the Structure app or Big Picture app when you pull anything linked on Gantt diagram? Do I have to create rules for this, or Jira has built-in functionality?
Hi @Dmitry
Can't say that I comprehend 100% your problem. Are you referring to jira's roadmap? Any screenshot of what you currently have, or what you are trying to accomplish, it would be of great help.
I meant rescheduling dependencies. If a "blocking" task's due date is adjusted to be later, it should automatically move the start & due date of the connected 'waiting on' tasks by the same amount of time
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for clarifying this @Dmitry . Issue linking do not provide such functionality. Writing rule for moving dates would be one way to go. The other would be to use an app from the marketplace.