Critical Path in BigPicture

Kara Heuer February 18, 2020

 

BigPicture is marking a 'milestone' task as the Critical Path for my Gaant chart. Is anything I can do to make the Critical Path evaluate actual work tasks rather than milestones?

1 answer

0 votes
Patryk-SoftwarePlant
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 6, 2020

Hi Kara,

At this moment, milestones are treated as tasks on a critical path, but we are planning to rebuild milestones soon. Keep track of ONE-6499. In case of having trouble accessing the link, you may try Incognito.

Cheers,

Patryk