Hi
I want to plan some hours to certain users , for example 4 hours per day for 2 days.
But the user instead of using the 4 hours on day 1, he used only 3 hours (or 5). Can this 3(or 5) hours be seen on the Planned Resource view?
So I can effectively see what can I, as a coordinator, plan more or less hours next day?
Hi Cesar,
when you have Tempo Timesheets installed you get a planned vs actuals report that will show you the planned time on a project/issue/resource versus what has been tracked against them.
https://www.tempo.io/blog/the-planned-vs.-actuals-report-in-jira-with-tempo
BR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Cesar,
you can choose a different option under group by.
If you want to have more options there you could submit a feature request.
BR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Alexander, Yes I can group by User , but could not find by issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Cesar,
yes you are correct. Planned vs Actuals report only allows a grouping by Epics. You could submit a feature request to add an option for grouping by issue.
As a workaround you can pull a Timesheet report showing both planned and logged time and group it by issue.
BR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.