Can't linked in between 2 issue in BigGantt JIRA

muthia.iftinah August 12, 2020

Hi everyone, i got this information when i want to make a dependencies between 2 issue:

"Link is invalid. It lacks a source task, target task or type of link." Please help me find out why and what i'm supposed to do. Thank u

1 answer

0 votes
Marcin Geb _SoftwarePlant_
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
September 1, 2020

Hello

How are you trying to create that link? Are you dragging and dropping from one bar to another in the Gantt chart?

Constraints do exist, though. For instance, I couldn't create a start-to-end link from P1M to P1M-42 - see the "error" to which the green arrow points to.

I'd need a screenshot or two, representing your particular setup, to be able to help.

constraints-within-gantt-chart.png