BACKGROUND: Several of Control Chart Gadgets were calculating issues' life cycle data depending on certain statuses, i.e. "Ready for Prod".
PROBLEM: We made an additional bulk change that transitioned many issues once more through the "Ready for Prod" status. Hence, now many issues have duplicated transitions to the same status and data in the gadgets are negatively affected, lifecycle is way too long because Time in status added up additional time range.
IDEAS to solve:
- undo a bulk change (as I know we dont have such function in JIRA)?
- delete a record from history (is there a way to do so?) i.e. delete the duplicated Time in status?
- maybe we can setup the control chart gadget in any way so it would exclude hourly range when the duplicated status was made?
You can consider Time Between Statuses app. It lets you set different statuses for the time counter`s start and stop. Additionally, this tool lets you set extra conditions for timer triggers such as first/дфіе transition to/from status.
Hope this function will help you calculate cycle and lead data in the way you need.
Regards
The manager’s daily activities include a list of challenges to reach high levels of efficiency for their teams. Part of these challenges is related to how to deal with the worklog systems sin...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.