Bigpicture - what's happens with the hours planned that are not registered in Tempo Timesheets??

Sandra Carrillo January 20, 2022

Hi,

We have integrated BigPicture Enterprise with Tempo. We know that the teams, the workload schedule and holiday plans are synchronized.

When we enter time in Tempo Timesheets, we see that the field "Time spent" increase. What happens with the hours planned and not entered in Tempo Timesheets?

For example, we plan a task with 8 hours/day effort for our resource. If the resource only enter 2 hours, what's happens with the 6 hours remaining? the end of the task move? 

Thanks!

1 answer

1 vote
Anna-BigPicture
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
January 28, 2022

Hi @Sandra Carrillo

It depends on what Effort Mode is enabled. If you have the remaining estimate mode enabled, then BigPicture will display 6 hours for today and the future. But if you use the original estimate mode, the app will display the value of the Original Estimate field = 8h.
 
The task end date depends on what field is mapped in App Configuration. Please find more info in the article: BigPicture tutorial - Dates synchronization.
Sandra Carrillo January 28, 2022

Thanks for your answer Anna!

We are looking for this article but the option "Time Spent + Remaining Estimated" does not appear. 

 

Capture2.PNG

For clarification, we have Bigpicture and Bigpicture enterprise on cloud.

Can you help us, please?

 

Thanks!

Like Anna-BigPicture likes this
Anna-BigPicture
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
January 31, 2022

Hi @Sandra Carrillo

The option to map the End Date field to the 'Time Spent + Remaining Estimate' is not available at the moment due to an error. However, I am pleased to let you know that it has already been identified and fixed. The bugfix will be released in coming this week in the 8.3 version.

Like Deleted user likes this
Sandra Carrillo January 31, 2022

Hi Anna,

Thanks for your answer!

We have seen that we change the "original estimate", "remaning estimate" does not refresh.  Do you know if this is the correct functioning?

Thanks! 

Like Anna-BigPicture likes this
Anna-BigPicture
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
February 1, 2022

You are welcome @Sandra Carrillo

Switching between effort modes: Original estimate mode - Remaining estimate mode should trigger data recalculation. Please clear the plugin cache (App Configuration >> Advanced >> Clear Cache).

If this will not resolve the problem, reach out to our Technical Support via our Service Desk. This will allow our product specialists and developers to investigate your case individually and provide you with a solution.

Like Deleted user likes this
Sandra Carrillo February 1, 2022

Thanks Anna,

How can I clear cache of Jira? I've just cleaned cache of Bigpicture, but the behaviour is the same as commented before.

Thanks!

Anna-BigPicture
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
February 4, 2022
 Dear @Sandra Carrillo , I've searched Atlassian documentation, and unfortunately, I didn't find any instruction in this matter.
I highly encourage you to contact our Technical Team. An in-depth, individual investigation of your instance is the best option. I can assure you that team is highly qualified and ready to resolve your issue. 
Contact our Service Desk - here.