BigGantt: duration in calendar days

Giovanni Stoto December 16, 2020

I need to use BigGantt for creating schedules based on a very simple concept:

- I create a task

- I set startr date

- I define duration in calendar days

- End date is automatically calculated

 

Seems impossible as there is nor DURATION field in Biggantt.

1 answer

0 votes
Anna-BigPicture
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
December 17, 2020

Hello @Giovanni Stoto

Currently, there is no possibility to calculate the End Date based on a period (in days). However, we are aware that this functionality is very useful for our clients, and it’s already on our Roadmap.

You can follow work progress in the feature request ticket: ONE-1727. Please note that it is best to open it in the incognito tab of your browser.

Best regards,
Anna

Suggest an answer

Log in or Sign up to answer