Big Picture Task Duration

Andy Atkinson May 12, 2022

How is the duration of a task calculated in Big Picture? In MS project I create a task, give it an effort estimate, assign one or more resources and I get a duration. Is it the same in the Big Picture:

task = jira issue

effort = original estimate (say 40 hours)

resource = assignee (with a working day of 8 hours)

duration (days) = original estimate / assignees working day

= 40 / 8

= 5 days.

2 answers

1 vote
Fabian Lim
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 12, 2022

Hi @Andy Atkinson

Yes, that's how it's calculated. Bur you have to ensure that you have a start and end date set in your task with the effort (time tracking).

Link: https://bigpicture.one/time-tracking-bigpicture-biggantt/

Regards

Andy Atkinson May 12, 2022

If I am manually setting the start date and end date then am I not also manually setting the duration?

If I have a start date (which I believe is equal to Jira Creation Date, by default) and I know the effort (Jira Original Estimate) and I know the resource assigned (Jira Assignee) and their working hours per day, isn't the end date calculated for me?

End Date = Start Date + (Effort / assignees hours per day)

End Date = Mon 1st Jan + (40 hours / 8 hours per day)

End Date = Mon 1st Jan + 5 days (the duration!)

End Date = Friday 6th Jan

In MSP I only enter end dates or a duration for tasks that are 'fixed duration', not effort driven. For effort driven its almost always a start date, an effort estimate, and one or more resources (with a resource % allocation).

I don't understand what Big Picture needs Start Date and End Date to 'calculate' a duration....clearly I am missing something here...

Fabian Lim
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 17, 2022

You will have to ask bigpicture directly. It's mandatory for their calculations, but I had the same concern as you. 

Feel free to try other apps as well such as structuregantt or wbs gantt chart.

Regards

0 votes
Anna-BigPicture
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
May 19, 2022

Hi  @Andy Atkinson

A task duration depends on the synchronization you set in App Configuration. Please look at the article BigPicture tutorial - Dates synchronization to learn more. 
I will be more than happy to answer your further questions.
Andy Atkinson May 24, 2022

Hi @Anna-BigPicture 

Perhaps you could tell me exactly what the configuration needs to be (in the app configuration, which drop downs to change from the defaults, and what the change them to) to have duration calculated in the way I expect in my message. i.e. the end date and duration are calculated based on the start date, the original estimate, and the allocated resources working hours.

The documentation you point at is not sufficiently clear on how to configure the tool to achieve this.

Thanks.

Andy Atkinson May 30, 2022

@Anna-BigPicture - any further update / assistance with this one?

Thx

Anna-BigPicture
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
May 31, 2022

Hi @Andy Atkinson

In summary, you want to schedule your project based on tasks' Original Estimates and Assignees' working days?  
 
Please go to BigPicture App Configuration >> General >> Tasks (please note that only Jira administrators can access this page).
image (28).png 
The next step depends on the expected outcome. If you want to use this configuration only in a specific project (not general settings, which will be applied to all BigPicture projects), on the right, you will see a button "Add project." Once you click it and select Jira project, you will see a dropdown list next to Start Date & End Date. 
Please select Start Date to map Start Date and Original Estimate to map End Date. 
image (29).png
 
There is only one step missing. On the bottom of the same page, enable the "Calculate tasks automatically based on assignee's working days" to adjust a task duration to individual resource capacity. Save settings. The end dates will be automatically updated.
image (30).png
 
I hope this helped. However, if you need more specific information, simply tag me!
Andy Atkinson June 26, 2022

Hi @Anna-BigPicture

Sorry for the delay. I made the changes as outlined above, and nothing changed. I have a task allocated to myself, and there is no change to the task duration / end-date whether I am 50% or 100% available in the resource / workload planner. I would expect the duration to double in the case where I am only 50% available.

Thoughts?

amit_hergass August 1, 2023

@Hi @Anna-BigPicture 

Do you have an answer for the % allocation question above, as it is not working for me as well.

Further on this, will it be possible to have % allocation on the Task level? So an individual will be able to work on a number of tasks in parallel with different % allocation on each task. The Due date should be calculated the same way as above, i.e. Due Date =  Start Date + ( Original Estimate extended based on % allocation )

Example: Assume a task with O.E of 2 days, the task is set with 50% allocation of the assignee. In this case I would expect to have the Due Date set for 4 days after the Start Day. 

Thanks

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events